Loading...
HomeMy WebLinkAboutURA RES 2016-23 RESOLUTION NO. aOI 4,- BE P-BE IT HEREBY RESOLVED by the Chairman and Commission of the Caldwell East Urban Renewal Agency in the City of Caldwell, Idaho, to authorize payment to Idaho Power for relocation of utilities adjacent to the vacated portion of Slipstream Way and extension of 3-phase electrical power service through joint trench to the Fresh Project Site in the amount of$92,199.00. PASSED BY THE COUNCIL of the City of Caldwell, Idaho this 11t day of July 2016. APPROVED BY THE MAYOR of the City of Caldwell, Idaho this 11t day of July 2016. Approv By/ �` ,of U' airman ATTEST: y . •_� \LA .4 _ URA Secret ,ssss,.e•,,,,,,,,•, �.t cyl Y OF •. c Q- • _ /• ~ ! GE. IDAHO CUSTOMER COST QUOTE An IDACORP Company IDAHO Customer or Project Name: Design Number: Version: Work Order#: CALDWELL URBAN RENEWAL AGENCY 2-EXTEND 3-PHASE BA 0000116787 002 27459814 Line Installation Cost Prepaid Fees Debit Credit Totals 1. Line Installation/Upgrade Costs 70,605 2. Company Betterment/Other Credits 0 3. Salvage IPCO-Credit 0 4. Customer Provided Trench 0 5. Net Line Installation Cost 70,605 Terminal Facilities 0 6. Terminal Facilities 7. Customer Allowance 0 8. Salvage Term Credit 0 9. Net Terminal Facilities 0 10. Unusual Conditions 5,840 11. Bank Letter of Credit ( 0 (Only for Unusual Conditions over$10,000) 12. Net Construction Cost 76,445 13. Net Vested OR Refundable Construction Cost 62,324 (Limited to 5 years or 4 additional applicants) 14. Construction Cost Not Available for Vesting or Refund 14,121 Other Charges 15. Vested Interest Work Order# 0 16. Billable Permits 50 17. Prepaid Permits $ 0 18. Billable Engineering Charges 0 19. Prepaid Engineering Charges $ 2,380 20. Underground Service Attachment Charge 0 21. Relocation or removal with new capacity 0 22. Relocation or removal with NO new capacity 15,704 23. Salvage Credit Relocation 0 24. Miscellaneous Charges/Adjustments 0 25. Net Other Charges 15,754 26. Total Work Order Charges $ 92,199 27. Idaho Power Co. Contribution &Other Credits $ 0 28. Total Customer Payment Due (Line 12 + Line 25) $ 92,199 Customer signature is required on Page 2 of this document Notes: IDAHO Idaho Power Company Page: Date:61248016 ``. Service Request An IDACORP Company Service Request Number:00387027 CALDWELL URBAN RENEWAL AGENCY 2-EXTEND 3-PHASE BACKBONE Work Order Number: 27459814 Eng Hours. Request Type: CS Eng Fee Amount(Att98): 0.00 Rate Sch.: 09 Eng Fee Amount(Attl6): Reply By: Eng Fee Service Agreement No: Eng Fee Service Agreement Date: Customer No: Feeder: LN D N 18C Service Location: S SMEED PARKWAY CAI Required in Service Date: 6/17/2016 Planning Center/Team: NCANYON Contact Detail: CUST CITY OF CALDWELL 455-3000 PO BOX 1179,, CALDWELL ID 83606 CUST ROB HOPPER-CURA#2 208-880-9659 411 BLAINE ST,PO BOX 1179,, CALDWELL ID 83606 IPCO GREG EVANS 465-8615 2420 CHACARTEGUI LN,, NAMPA ID 83686 IPCO NICK SCHOONOVER 465-8651 Attribute Information RES/COM Service Voltage IZ•5 No.Of Meters NONE Number of Phases 3 PHASE Meter Location KW Motor Load: Ct Loc Largest Motor Primary OH/UG UG 1 Phase KW Demand Service OH/UG UG 3 Phase KW Demand Sry Owner IPCO Vested Int.Connected Load RELOCATION Panel Amp Size NONE Commercial Deposit Amount NONE Description EXTEND 3-PHASE UG PRIMARY CABLE FROM LNDN 18 CA1 TO NEW SWITCH GEAR TO SERVE NEW PROJECT FRESH RELOCATE EXISTING 3-PHASE FOR THE REPLAT&REMOVAL OF SLIPSTREAM WAY AS NEED SCHEDULE WORK THROUGH JOINT TRENCH SCOPE OF WORK: Aub 130 CO A0 B0 CO INSTALL NEW 750 3/o PRYARr p0000p p0000p p00004; 9 0000 0000 0000 INSTALL NEW PME 31,CUT M A SECTOR AND W tO O W W W W<O O W W W W t0 0 W t` Q00004)p Q p p p REROUTE ME PRIMARY W O W Oj j d O O C3 j `` W COO)W n L. W CO 0)W n, ,CO O)lan W 01 1 0 0 1 1 0 0 1 I 0 PA a 0 40ND� WO WONT WO ON,I,5 L. OV)NOND ON UI,„0-....CL- C3 V) UI0 +.�.o:r. a a a v z z z ? ? I w O N O O O O N 0 34. N Uf U1 fA V1 to C-Z Z Z Z Z Z W W W W W SD-8 AO BO CO SD-86 1..N.N.I p0000p p0000p p0000p It(O—W W W IO W W W W to W W W 4 0°0 i�d�d`` 1`ooaaaO ``c3o oo.a.O `- op 00.0_0 00I D_0_0_O OpadaO 0 0 to Ln to 0 0 to N Ul 10 0 0 0 N V)V)0 Z Z Z Z Z Z 0 W W W W N M 1` ' 1 A0 Bo CO SD-9 K 75 501 CA-1 : Customer or Project Name: Design Number: Version: Work Order#: CALDWELL URBAN RENEWAL AGENCY 2-EXTEND 3-PHASE BA 0000118787 002 27459814 ,an 4 ACORr COMOVN Unusual Conditions Acknowledgement Unusual Conditions are construction conditions not normally encountered. These conditions may include, but are not limited to: frost, landscape replacement, road compaction, pavement replacement, chip-sealing, rock digging, boring, incomplete customer trench, nonstandard facilities or construction practices, and other than available voltage requirements. I have read and understand the above definition of Unusual Conditions as set forth in Idaho Power Company's Line Installation tariff, Rule H. I further understand that Idaho Power Company will determine the type and extent of the Unusual Conditions encountered. Unusual Conditions charged for on the Customer Cost Quote sheet, but not encountered, will be refunded to the Customer by Idaho Power Company after the completion of construction. / Signed: ►`I /Customer Signature Date: 7 —// -Zed (a 4 IDAHO Idaho Power Company Page:2 Date:6/24/2016 1►- Service Request An IDACORP Company Service Request Number:00387027 CALDWELL URBAN RENEWAL AGENCY 2-EXTEND 3-PHASE BACKBONE I understand that the information provided above is accurate to the best of my knowledge. Changes to load;voltage; location; etc ma :.ult in add' ional charges. 7—// -zol‘ //' U/E - zV/fr lient Signatur Date Idaho Po er Representative Signature Date 1; Customer or Project Name: Design Number: Version: Work Order#: CALDWELL URBAN RENEWAL AGENCY 2-EXTEND 3-PHASE BA 0000116787 002 27459814 Total Customer Payment Due Prior to Construction Scheduling $ 92,199 Notice:This Customer Cost Quote shall be binding on both Idaho Power Company("Idaho Power")and Customer for a period of sixty(60) days from the date below indicated,subject to changes in information provided by Customer or changes in Idaho Power's ability to obtain satisfactory rights-of-way or to comply with governmental regulations,including but not limited to the rules,regulations,and tariffs of the Idaho Public Utilities Commission("IPUC")and the Public Utility Commission of Oregon("OPUC").Customer must make payment of the quoted amount not less than thirty(30)days prior to the start of the construction work set forth above(the"Work"),but Idaho Power does not represent that the Work will commence within 30 days of receipt of payment.The start of the Work is subject to Idaho Power's ability to obtain the necessary labor,materials and equipment. Prior to commencement of the Work,Customer shall identify for Idaho Power the location of all underground pipes,lines,and other facilities(collectively,the"Underground Lines")that may be on Customer's property where Idaho Power is working.Customer agrees to be responsible for identification and location of all Underground Lines and shall indemnify,defend,reimburse and hold harmless Idaho Power and its successors and their respective directors,officers,members,employees, representatives,and agents for,from, and against any and all claims,liabilities,losses,damages,expenses,suits,actions,proceedings,judgments and costs of any kind (collectively,"Damages"),whether actual or merely alleged and whether directly incurred or from a third party,arising out of or relating to Customer's failure to properly or adequately identify and locate the Underground Lines,except to the extent finally determined by a court of law that such Damages resulted from the gross negligence or willful misconduct of Idaho Power, its agents,subcontractors,employees, officers or directors. Customer acknowledges Idaho Power's Rule C(Service and Limitations),Section 7(Rights of Way)on file with the IPUC and OPUC:"The Customer shall,without cost to the Company,grant the Company a right of way for the Company's lines and apparatus across and upon the property owned or controlled by the Customer,necessary or incidental to the supplying of Electric Service and shall permit access thereto by the Company's employees at all reasonable hours."By signing this form,Customer grants to Idaho Power a perpetual right-of-way over Customer's property for the installation,operation,replacement and maintenance of power facilities to provide electrical service to Customer and any future owners of Customer's property. // (Customer Initials) Charges for relocation,transfer or removal of non-Idaho Power equipment attached to Idaho Power Facilities are not included in this Cost Quote. It is the Customer's responsibility to coordinate this work with the affected utility. All charges ' associated with this work are the responsibility of the Customer. For utility contact information,please call 208-388-2886. /, i (Customer Initials)Charges for installation of underground electrical service are not included in this Cost Quote and will be billed to Mil e customer after work has completed (Customer Initials)The stom=r acknowl-.ges receipt of the reduced charge option brochure/packet,also available at idahopower.com i l 20k Customer Signature X / Ild#11iibi. ,1/� Date X 7 /— 1 IPCo Representative X L iC' 004 d e ;„: Quotation Date X t o 1" `fir- VESTED INTEREST REFUND WAIVER NM. An DACORP Company This Vested Interest Refund Waiver("Waiver") is entered into by and between Idaho Power Company, an Idaho corporation with its principal offices located at 1221 W. Idaho Street, Boise, ID 83702("Idaho Power")and City Of Caldwell Customer Name with its principal offices located at Po Box 1179 Mailing Address City State Zip ("Customer"). Customer funded the installation of distribution facilities,pursuant to Work Order Number 27459814 necessary for Idaho Power to provide kW ("Customer's Connected Load") of electric service to Customer's facility located at So. Smeed Parkway Caldwell,Id.83605 , in the County of edj(/f/Qjv State of Idaho. Pursuant to Customer's funding, Customer is a Vested Interest Holder in the total amount of$ 7(v! .f C I5 , as defined by Rule H of Idaho Power's Tariff,titled New Service Attachments and Distribution Line Installations or Alterations("Rule H"). As a Vested Interest Holder,Customer is entitled to Vested Interest Refunds,as defined by Rule H, and makes the following election with respect to the same: jgiCustomer waives all Vested Interest Refunds. ❑Customer waives any Vested Interest Refunds for Connected Loads of Additional Applicants(defined by Rule H)of less than or equal to kW. Customer acknowledges that Idaho Power has provided them with information on Rule H, and that the Customer can also access the same information from Idaho Power's website at (www.idahopower.com)or the Idaho Public Utilities Commission website(www.puc.idaho.gov). Customer further acknowledges that Customer has certain rights and obligations contained in Rules H which are not fully detailed in this Waiver, and that Customer is responsible for understanding and com•lying with all such rights and obligations. Iii 4- ii. CLev-1,4".. ctu 7- 1 -2x/6 usto' er ig' 'r,re it e Date Nick Schoonover Din. Des eG dez. June 24,2016 Idaho Power Representative Title Date 1 1 ., 1 II, MEMORANDUM To: Chairman Hopper and Caldwell East Urban Renewal Commissioners From: Brent Orton,PE,MSCE Public Works Director Re: Authorize Payment to Idaho Power for Electrical Extension in the vicinity of Smeed and Slipstream Date: July 6,2016 Requested Action: Approve authorization of payment to Idaho Power to extend 3-phase power to the Project Site located generally at Smeed Parkway and Slipstream and remove power on the portion of Slipstream recently vacated by the City of Caldwell. A 3-phase power service is needed to accommodate the anticipated loads and power requirements for a manufacturing facility known as project Fresh.The attached resolution authorizes payment to Idaho Power to relocate old joint french in the vicinity of the partial Slipstream Way vacation and to extend appropriate 3-phase UG primary cable for the manufacturing site. Payment amount to Idaho Power for the extension is$92,199.00. The Caldwell Public Works Director has reviewed the attached resolution and recommends that it be approved.