HomeMy WebLinkAbout1979-05-18 Stadium Advisory Board Stadium Advisory Board Meeting
1 May 18, 1979 - 12 Noon
City Hall, Council Chambers
Caldwell, Idaho
Present : Alta C. Williams :Darrel Deide
Mayor Pasley Dick Carrow
Guests : Stan Pilcher :Dwight Comfort
Dave Baker, Tex Coles
Chairman Williams opened the meeting at 12:10 and ask Dave Baker
for a report on the estimate on improvements at the complex.
Dave opened his report with the statement that the estimate did
riot include the wash racks . It does include removal of and re-
placement of the concrete pad that is behind the fieldhouse. It
includes the grading and the paving of the area between the fieldhouse
and the charolais barns from the southeast edge of the fieldhouse
down to and including the curb and gutter on 22nd Street. The big
paved area will run right to the fence, there will be a catch basin
inside the fence but out of the gate area, and drop into the drain
line. There is a section of curb and gutter that we feel should be
extended at the same time. Some of these things can be broken down
if the prices get unreasonable. The section of curb and gutter
really needs to go around the corner to the catch basins so that
the street is properly drained. You are probably aware that it is
a problem out there now. It includes a water line; replacement of
the plastic line that is there now, just outside of the concrete,
running that in cast iron across to the charolais barns - across
what would be the Paved area, but it doesn 't include any plumbing
in the charolais barns - just over to there. Darrel said there are
)I to 6 faucets in the barns now. Dave said if we could connect to
that system it wouldn' t be a problem but the estimate didn 't include
any extra plumbing In the barns themselves . There is a buried power
cable from. the building out to the barns now and it may have to have
another line running out there to get the proper amount of power.
That cost is included in this, also.
Darrel said they have to have morn power, both for the 4-H and for
the charolais, because they don't have enough power to operate their
clippers and all the things that they have to have.
Dave said they estimated that the excavation,the base material that
will go back in and the asphalt surfacing would all be done by City
forces. They are better equipped. The curb and gutter; the driveway
approach; the catch basin and the concrete flat work we assumed would
be contracted out. Mayor said we don' t want to bid that.
Dave said since the cost of the flat work is $?262 and the catch
basin is another S1+00+ and the driveway approach. The complete thing
is less than $5, 000 and we wondered if we could get permission not to
bid that but to contact 3 or 4 people and negotiate. Number one it
would take a long time to bid it. The problem we have had in the
past is getting someone to come in and do the work.
The total figure including the water line and design of the whole
thing comes to about 215,23$1. Again, that does not include the wash
e , racks.
Mayor Pasley said the improved area between the fieldhouse and the
charolais barns will eliminate where they have presently been doing
some washing. Dave said they can still wash there, as there are
3 hydrants directly behind the building and the intent was to continue
to use that as a wash rack if needed. It is graded so the water will
run away from the building and down to the catch basin. The 215,234
does include the concrete.
Alta inquired as to when the work could be started. Dave said the
street crew could start removing concrete Monday, the 21st, and Jack
is scheduled to put the water line in some time the end of the week,
he believes. The excavation for paving will probably go on at the
same time as the concrete removal. It would probably be a 2 week
project. Mayor Pasley said it is just a matter of getting someone
to do the concrete work.
Darrel said the 4-H hair starts July 23rd. Alta said she thought
Little Britches starts the 10th of July.
Darrel ask for the package again. Dave said it includes the excavation,
the base material, the asphalt surfacing for the area between the
buildings, 109 ft of curb and gutter, a driveway approach for the
)gate, 2 catch basins - one :i n the street and one in the yard itself,
i0 rt. of 12" pipe and 1740 sq . i't. of concrete flatwork. The concrete
will go right up next to the building. Where the existing concrete
is now, that will be removed and the whole thing lowered and sloping
cew'cy f'rein the building. Darrel said why not make small steps by the
hack doors and put asphalt on the rest of it. Dave said because if
we made the wash racks, we would not want the wash racks asphalt, so
that, area wouid probably have to be concrete and rather than. break it
up we ran it all concrete. Dwight said IT you put cattle on asphalt
it would deter' oratc.
Darrel said ; ,a eht the water should be channeled so it doesn 't
have to rk , ver the asphalt area. Dave said we could put drains
up next to i concrete but it would be considerably more expensive.
Dave said there is a valley in the asphalt but it is quite a long
valley, but it docs require that it flow across the concrete out
over the asphalt and down to the catch basin. It is possible to put
a drain right on the low edge of the concrete for 50 or 75 feet. More
expensive, but it can be done. That would stop the backflow before
it even gets t-o the asphalt.
Mayor Pasley ask if we built wash racks close to 22nd Street and
eliminated any concrete between the f:ieldhouse and the charolais
barns, so there would be no cattle washing there, could we save
enough to defray half the expense of building the wash racks? This
would be the ideal situation :i r we could keep the washing away from
the f:i eldhous e.
Dave sa:id the concrete flatwork will cost $2262 and that much asphalt
would run about $7,000, so there is considerable saving.
More discussion on putting the wash racks along 22nd Street. Mayor
/'N said they could then drain directly into the drain line. Alta asked
if we would have enough money. Dave said he thought so. He asked
what size wash racks we are considering . Mayor Pasley thought 6 would
be about right and Dwight thought )4 at a minimum. Dave - what area
per wash rack are we talking about? Dwight thought about 6' x 8' .
Dave said that is a lot less concrete than what we would be eliminating.
Plumbing would have to be there. That would require 6 hydrants, 6
drains and a line out to the drain line. We would have S1562 to work
with to build wash rack. It has to be concrete. City could do every-
thing but the concrete work. Concrete work would run about $700 so
that would leave about the money for plumbing.
As for the design of the wash racks, Darrel would prefer that Darrell
Bolz or someone familiar with affairs there to pinpoint where the
they should go. Alta thought maybe the man from the Charolais should
be there also. Darrel said their main concern was frozen water lines -
no water and the electricity. wasn ' t ample .
Darrel ask about our financial situation . Alta said the scoreboards
are paid for. Two payments or, the seats have been made. Insurance
has been paid. Also a .mei scellrneous $220 or $250. Our balance after
revenue ti harli tf; of $15,000 and $6, 000 from the rodeo we have S25,973.91.
The irrigation toll has not been paid and we don't know how much we
will have to pay on the O'Connor Fieldhouse sign because we do not
have the moh, Yor all of it. The total donated up to this time is
$750 and the eee was over 51,700 so we have to allow for that. We
should pre Pai, H Hee out $2,000 for the irrigation toll and the sign.
Mayor Paele. jRught the estimate for the fencing and the paving under
the bleachers ws approximately $5,600. He things the kitchen will
have to come irst which will probably be about $5,000.
Darrel was going to make a motion but Alta said we have approval
from the Council. Lo spend everything that is coming in this year.
Alta said. the Pre chief reported the concession stand has to be
.leaned up. `:ent, i_.lation must be put in the kitchen and we have to
do something about the floor, either put in a new one or put linoleum
down.
Darrel asked Dave if they could get together with the fire chief and
someone from Idaho Power and go up and take a look and see what has
to be done and also see about the cost. Alta said the wiring under
the floor should be checked and repaired if needed. Several plug-ins
de not work . They will report on this the next meeting.
Alta asked Dwight if he would like to say something. Dwight said
the F-.j.r Board realizes we are trying to improve the site but they
have been treated as an orphan child, they couldn't get help when
they needed it. There is a feeling amongst the board they want multi-
purpose units which have carnivals , can have commercial displays in the
f_i_eldhouse along with the 14-H Fair which they cannot do now because
of size limitations . They want room. for fine arts in the n 'ibits .
Photography and painting. They feel there isn' t sufficient area.
They don't know when or if they- can do anything-
,/N Alta thought 2e;r that kind of facility she would guess a long way
down the ron'' , because of money. Mayor Pasley said there is four
acres up there that would be better than going out and buying a
large piece of land because so many of the facilities are right
there and. arc 'paid for, and every ,year there are more improvements
being made.
Dwight said tJle minimum for setting up e. carnival is twenty acres .
That allows for parking, setting up and midways. The four acres are
fine but it would be difficult for them to buy four acres and put any
kind of improvements to it when the adjacent property may not be
there or may not be available to them at some future date. That
type of acquisition would tend to be a deadend acquisition or could
be at some time.
Mayor Pasley said there is no reason why the stadium., if the county
wished, couldn' t sell an interest in the rodeo grounds , charolais
barns or any of that area which is quite well improved. It ' s the
additional area where the pinch comes in. Definitely the City won't
have money In the foreseeable future for land acquisition.
Alta asked if the comrmm_i ss:i_oners had anything to say. Mrs. Coles said
they haven 't officially received their recommendation from the Fair
Board. Cf course they know there .is no money as it wasn't budgeted
for. Alta asked if they were going to be able to put the levy back
on. Mrs . Coles said not without legislative action.
Darrel said after we get the work done around the fieldhouse and the
concession we should look to getting the work done under the bleachers
and the storage.
Meeting adjourned 12 :50.
Arleen Abrahams
ecretary