HomeMy WebLinkAbout03 Public Agency PUBLIC AGENCY
ITEM DA'l'E SUBMITTED BY
24 - 10107ite
Memorandum
To: Linda James
From: Gordon Law, City Engineer .10
Re: Case No. SUP-85-00
Request for Special Use Permit by Matterhorn Ice Cream
Date: May 16, 2000
The Engineering Department has reviewed the referenced request for a Special Use Permit and
provides the following comments:
1. The Engineering Department does not object to an additional building on the site.
2. The right-of way for Plymouth Rd. is adequate for street purposes and no additional right-of-
way will be requested as part of this permit.
3. The Infrastructure Policy requiring curb and gutter and sidewalk does not apply to this site,
because the proposed additional improvements are less than 40%of the existing improvements.
Also,the City is considering a project to demolish the existing concrete paving and replace it
with asphalt in a project in the near future. The providing of street side improvements prior to
the completion of that project would be counter-productive.
4. Any new impervious area created in conjunction with this building must be dealt with in
accordance with the City of Caldwell Storm Drainage Policy.
5. The new structure must be hooked to City sewer and water.
r G;; DWEL�r� �.
9� CALDWELL FIRE DEPARTMENT
a
CIiY OF CALDWELL
I 310 South 7th Avenue Protecting Your Property Saving Lives\ CALDWELL, IDAHO 83605
\ 11C (208) 455-3032
OresTo 0{t¢
DATE: May 16, 2000
TO: Linda James, Community Development Director
FROM: Douglas Brown,Fire Marshal
SUBJECT: Comments for Caldwell Hearing Examiner (May 25th Hearing)
The Caldwell Fire Department offers the following comments regarding cases to come before the
Caldwell Hearing Examiner on May 25, 2000:
Case No. ANN-31-00/Jan M.Vinson
48 Acre annexation /Vicinity of Linden and KCID Rds.
No comments on this annexation at this time.
Case No. SUB-49-00/Reed Taylor,Applicant
Caldwell Commercial Park Subdivision #2/Aviation Way
The CFD has received plans (Permit #28552) to develop a truck wash facility on Lot #2 of this
subdivision. We are currently awaiting further information from the architect before conducting the
plan review. The CFD does not oppose this proposed project as long as all conditions are met and
adhered to by the developer/builder.
Case No. SUB-30F-99/V.E. Graves and Sons,Inc.
Quail Meadow Subdivision/Final Plat Map Approval
Upon approval of the final plat map CFD will assign the addresses for the lots in this subdivision.
Case No. SUB-34(1&2)F-99/
Southern Heights Subdivision /Final Plat Map Approval
Upon approval of the final plat map CFD will assign the addresses for the lots in this subdivision.
(continued)
� V
p
•
Case No. SUP-84-00/Robert P. Hurtt
1018 Albany/planned unit development(4 dwelling units)
Comments will be reserved until plan review of building peuuit application.
Case No. SUP-83-00/Don and Cheryl Lane
Mini-Storage Complex/341 units—9,200 SF structure+ 1,000 SF Office
1311 Andy Lane
Comments will be reserved until plan review of building permit application.
Case No. SUP-85-00/Matterhorn Ice Cream,Inc.
Modular office at 115 E. Plymouth
Comments will be reserved until plan review of building permit application.
Case No. SUP-11(A)-97/Nicole Lewis and Roxanne Hansen dba. Bean Hopper
2021 Cleveland Blvd.
Expansion of food service operations for serving additional food products on premises is not a
problem. Cooking of food products on-site may require special fire protection requirements that
would be addressed during a plan review.