March 26, 2026 Jonathan Robertson Classic Jack Construction
231 N. 300 E Orem, UT 84057 RE: Performance Bond for Nottingshire Heights, Street Buffer Mr. Robertson,
Below is the bond amount for Nottingshire Heights calculated as outlined in City Code section 10-03-17. As stated in City Code Section 10-03-17 (3) financial guarantees may be in the form of cash deposited, cashier’s check, or surety bond and held by the City until final completion of the development.
Nottingshire Heights – Street Buffer
Project Item % Complete Bid Amount Bonding Amount
Sub-Total
Financial Guarantee
Amount
150% of Total $ 5,220
This application has a fee of $335.00. This fee shall not be included in the bond and shall be paid
separately.
If you have any questions please feel free to contact me. Joe Dodson
Principal Planner 205 S 6th Avenue, Caldwell, ID 83605
P: (208) 455-4523