HomeMy WebLinkAboutBond Amount Letter 2026_ChestnutHeightsNo2 (2)
May 27, 2026
Cory Lockwood
Trilogy Development
9839 W. Cable Car St. Suite 101
Boise ID 83709
RE: Performance Bond for Chestnut Heights Subdivision No. 2
Mr. Lockwood,
Below is the bond amount for Chestnut Heights Subdivision No. 2 calculated as outlined in City
Code section 10-03-17. As stated in City Code Section 10-03-17 (3) financial guarantees may be
in the form of cash/check deposited, cashier’s check, or surety bond and held by the City until
final completion of the development.
Chestnut Heights Subdivision phase 2
Project Item % Complete Bid Amount Bonding Amount
Landscape (Buffers and
Common Area)
0% 398,275 597,412.5
Fencing 0% 163,872.29 245,808.44
Sub-Total 562,147.29 843,220.94
Financial Guarantee
Amount
150% of Total $ 843,220.94
This application has a fee of $335.00. This fee shall not be included in the bond and shall be paid
separately.
If you have any questions, please feel free to contact me.
Garline Davis
Principal Planner