Loading...
HomeMy WebLinkAboutItemizedBid_ChickasawNo1_V2 Landscape Construction Sprinkler Irrigation Landscape Management Lawn & Grounds Maintenance Personal Gardener Personal Gardener Contractors License # RCE-38790Idaho Business License RCE #38790 Oregon Business License LCB #9490 Contractors License #RCE 38790 26-Jan-26 Chickasaw Subdivision - Job # 21206 (LS) ; 31206 (Steel) Caldwell Idaho, Chickasaw Phase#1 Unit Qty Nov '25 Qnty Dec '25 Qnty Price Total Pricing Nov '25 Billing Dec '25 billing Total Billed Left to bill Classs #1 Trees 39 Autumn Brilliance Apple Service Berry EA 5 152.49$ 762.47$ -$ -$ -$ 762.47$ Eastern RedBud EA 10 152.49$ 1,524.94$ -$ -$ -$ 1,524.94$ Golden Rain Tree EA 6 298.40$ 1,790.40$ -$ -$ -$ 1,790.40$ Spring snow crabapple (Class 1 on plans, Lavon counts it as class 2)EA 18 152.49$ 2,744.90$ -$ -$ -$ 2,744.90$ CLASS #2 TREES 25 -$ -$ -$ -$ -$ Columnar Norway Maple EA 8 152.49$ 1,219.96$ -$ -$ -$ 1,219.96$ Aristocrat pear EA 10 152.49$ 1,524.94$ -$ -$ -$ 1,524.94$ SHRUBS -$ -$ -$ -$ -$ Endless Summer EA 23 20.40$ 469.20$ -$ -$ -$ 469.20$ Slowmound Mugo Pine EA 18 20.43$ 367.74$ -$ -$ -$ 367.74$ PJM Elite Rhododendron EA 3 15.04$ 45.12$ -$ -$ -$ 45.12$ Sun joy pillar EA 75 20.43$ 1,531.91$ -$ -$ -$ 1,531.91$ Karl Forester EA 75 20.43$ 1,531.91$ -$ -$ -$ 1,531.91$ Blue oat grass EA 32 15.04$ 481.25$ -$ -$ -$ 481.25$ Little Bunny EA 19 15.04$ 285.76$ -$ -$ -$ 285.76$ Little Grappette Dayily EA 6 15.04$ 90.24$ -$ -$ -$ 90.24$ Boxwood EA 20 20.43$ 408.51$ -$ -$ -$ 408.51$ Goldmound Japanese Spirea EA 23 20.43$ 469.89$ -$ -$ -$ 469.89$ Red carpet rose EA 78 15.04$ 1,173.04$ -$ -$ -$ 1,173.04$ Yucca color guard EA 33 20.43$ 674.19$ -$ -$ -$ 674.19$ Nine Bark EA 24 20.43$ 490.20$ -$ -$ -$ 490.20$ Additional items: (Includes areas in common 8' strips)-$ -$ -$ -$ -$ Sod (Includes sod/prepping/laying)SF 101240 0.74$ 74,453.92$ -$ -$ -$ 74,453.92$ Annual Beds (includes compost and labor)SF 2788 0.73$ 2,023.81$ -$ -$ -$ 2,023.81$ Black Lava plus fabric (includes prep/fabric/rock install)SF 14840 0.70$ 10,448.25$ -$ -$ -$ 10,448.25$ Irrigation "Materials Cost Only"SF 118868 0.24$ 28,528.32$ -$ -$ -$ 28,528.32$ Irrigation "Mark-up and Labor to install"SF 118864 0.66$ 78,450.24$ -$ -$ -$ 78,450.24$ Concrete caps for walls C/O LF 282 33.98$ 9,582.36$ -$ -$ -$ 9,582.36$ 3'x3' Sandstone columns EA 3 1,860.25$ 5,580.75$ -$ -$ -$ 5,580.75$ 3'x3' Metal Caps Materials EA 3 143.98$ 431.94$ -$ -$ -$ 431.94$ steel 3'x3' Metal Caps Labor EA 3 206.02$ 618.06$ -$ -$ -$ 618.06$ steel 4'x4' Metal caps Materials EA 3 213.46$ 640.38$ -$ -$ -$ 640.38$ steel 4'x4' Metal caps Labor EA 3 186.54$ 559.62$ -$ -$ -$ 559.62$ steel Drains, soil, irrigation, and set pots EA 3 329.46$ 988.38$ -$ -$ -$ 988.38$ Chickasaw Metal Signs -$ -$ -$ -$ -$ Steel walls SFF 280 29.36$ 8,220.80$ -$ -$ -$ 8,220.80$ Concrete footings for walls (Materials and labor)LF 56 27.89$ 1,561.84$ -$ -$ -$ 1,561.84$ Legacy lettering symbols, Powder coating, weld stubs, labor EA 1 3,489.23$ 3,489.23$ -$ -$ -$ 3,489.23$ Grand Total 243,164.48$ -$ -$ -$ 243,164.48$ Should you decide to proceed with all or part of this project we would ask that you read, initial and sign each item below. ____This proposal will be honored for 15 days from the date referenced, and is subject to our confirmation thereafter. ____ Due to volatile material pricing and increased fuel costs, we can no longer honor our proposals beyond 15 days ____After 60 days from the date of the signed proposal, the above rate of $75.00 per man hour is subject to increase. ____We reserve the right to make necessary plant material substitutions based upon availability and hardiness. ____Upon acceptance of this proposal, we require a deposit of 50% of the estimated cost. This will allow us to schedule the work and procure the necessary materials. ____Landscape and Irrigation modifications and adjustments above this proposal will be billed as an additional charge of $75.00 per man-hour plus materials and equipment. ____If any electrical or plumbing work is necessary it will be the responsibility of the owner and is not covered within this proposal. ____All materials and workmanship will be guaranteed for one year from the date of installation. If balance due is not received within 45 days of final invoicing, above warranty will be null and void. ____There is no guarantee for the health of any transplanted plant material. Contractor will not replace any plants that die as a result of transplanting. ____This proposal will be honored for 30 days from the date referenced, and is subject to our confirmation thereafter. ____Monthly progress payments based on work completed will be due by the 10th of every month. The balance would be due Sincerely, Owner Acceptance: ________________________________________________________Date: _______________ Thank you for the opportunity to present this proposal. I look forward to working with you on this project. 4663 Ustick Rd., Nampa, Idaho 83687 (P) 208-461-5111 (F) 208-461-9544