HomeMy WebLinkAboutFireTime Extension (Formerly the Collections)So sorry, no issue with time extensions
From: Morgan Bessaw <mbessaw@cityofcaldwell.org>
Sent: Monday, February 9, 2026 2:42 PM
To: Alan Perry <aperry@cityofcaldwell.org>
Subject: FW: Painted Sage Time Extension (Formerly the Collections)
Hi Alan,
Just following up on whether you had any concerns about the two time extensions I sent you.
Thanks,
From: Steve Pendleton <spendleton@cityofcaldwell.org <mailto:spendleton@cityofcaldwell.org> >
Sent: Wednesday, February 4, 2026 10:24 AM
To: Morgan Bessaw <mbessaw@cityofcaldwell.org <mailto:mbessaw@cityofcaldwell.org> >
Subject: RE: Painted Sage Time Extension (Formerly the Collections)
Sorry Morgan, these slipped off my radar. I will get this addressed today for you.
We have no issue with the time extension for the Painted Sage with the below water availability note and a note that traffic impact fees will apply to this development.
I am reviewing Midland Meadows staff report now for Hallie so we can discuss more before giving a determination.
Thanks.
spendleton@cityofcaldwell.org <mailto:spendleton@cityofcaldwell.org> (208) 455-4683
From: Morgan Bessaw <mbessaw@cityofcaldwell.org <mailto:mbessaw@cityofcaldwell.org> >
Sent: Wednesday, February 4, 2026 9:24 AM
To: Steve Pendleton <spendleton@cityofcaldwell.org <mailto:spendleton@cityofcaldwell.org> >
Subject: RE: Painted Sage Time Extension (Formerly the Collections)
Hi Steve,
Any update from Hallie on these two time extensions?
Thanks,
From: Steve Pendleton <spendleton@cityofcaldwell.org <mailto:spendleton@cityofcaldwell.org> >
Sent: Wednesday, January 28, 2026 5:02 PM
To: Morgan Bessaw <mbessaw@cityofcaldwell.org <mailto:mbessaw@cityofcaldwell.org> >
Subject: RE: Painted Sage Time Extension (Formerly the Collections)
Morgan,
This site also falls within water pressure zone 2 and may require restrictions on permits until the City has the capacity to service them. Again I will need to confirm with Hallie prior
to an approval for the TE.
Water Availability Note:
City of Caldwell Public Works Department has reviewed the recently adopted Caldwell Water Facility Plan System and determined that certain shortfalls exist in water pressure zone 2 south
of Interstate 84, zones 3 and 4. While these shortfalls are being remediated, the Engineering Dept. doesn’t contest the approval of the Preliminary Plat and the construction of onsite
infrastructure, but reserves the right to hold any phase of final plat and associated building permits until adequate water is obtained within the affected zone. The Applicant is
encouraged to work closely with the Engineering Department to determine potential construction timing and impacts.
Thanks.
spendleton@cityofcaldwell.org <mailto:spendleton@cityofcaldwell.org> (208) 455-4683
From: Morgan Bessaw <mbessaw@cityofcaldwell.org <mailto:mbessaw@cityofcaldwell.org> >
Sent: Wednesday, January 28, 2026 2:32 PM
To: Dave Marston <dmarston@cityofcaldwell.org <mailto:dmarston@cityofcaldwell.org> >; Alan Perry <aperry@cityofcaldwell.org <mailto:aperry@cityofcaldwell.org> >; Steve Pendleton <spendleton@cityofcal
dwell.org <mailto:spendleton@cityofcaldwell.org> >
Subject: Painted Sage Time Extension (Formerly the Collections)
Hello all,
Does anyone have any concerns with a time extension for Painted Sage, formerly The Collections. Their CDs are in for review right now and they expire in February, there is a change they
will get approved before they expire but its slim. They were originally approved as ANN-20-05/PUD-20-02 and this will be their second time extension. As always, I will make sure to
let them know about traffic impact fees.