September 2, 2025
Attn: Steve Satterlee
email: stevenmsatterlee@gmail.com
RE: STE25-000005 – Kahari Apartments SUP Time Extension
Dear Mr. Satterlee,
We have received your request for a time extension for the special use permit associated
with Kahari Apartments development, SUP23-000010. In reviewing your request, it
appears that construction documents were submitted within the required 12 month
period and approved on September 25, 2024. We have therefore reviewed your request in
accordance with criteria in Caldwell City Code Section 10-03-04 and have determined the
following:
(A) Significant amendments to the comprehensive plan or City Code have been adopted,
however, they do not change the basis under which the special use permit was
granted.
(B) Significant changes in land use have not occurred in the area that will impact or be
impacted by the project.
(C) Hazardous conditions have not developed nor have been discovered that will impact
the project.
(D) Community facilities and services are adequate to serve the project.
Based on the above findings, the SUP expiration date is September 25, 2026. Please
note, since the application was first approved the City has adopted Traffic Impact fees,
which will be due at the time building permits are pulled. Additionally, future time
extensions up to two (2) years may be granted as determined and approved by the
director. With all extensions, the director may require the special use to comply with the
current provisions of this chapter
Please let me know if you have any questions.
Sincerely,
Morgan Bessaw, AICP CFM