Memorandum
To: Katie Wright, Planner II
Caldwell P & Z Department
From: TJ Frans, Project Manager
Steven Pendleton, Plans Examiner II
Re: CPM24-000001, DEV24-000001, PUD24-000002, SUB24-000011,
ZON24-000002 (Soterra #2 & #3)
Date: August 14, 2024
The Engineering Department provides the following comments on a request by Ardurra, on
behalf of Landex ID Soterra LLC, is requesting a comprehensive plan map amendment for
approximately 9.75 acres of the 38.07 acres of parcel R3258300000 , from B (Business) to
MDR (Medium Density Residential) and a rezone from C-2 (Community Commercial) to R-2
(Medium Density Residential, to include approval of a development agreement modification of
the original development agreement (Instrument No. 2022-012912) to allow for medium density
residential townhomes. Concurrently the applicant is requesting approval of a planned unit
development for approx. 15.79 acres of the 38.07 acres for a mixed-use development
containing 34 commercial lots and 23 residential lots containing duplexes, 4-plexes and 6-
plexes,for a total of 90 residential units; and for approval of a modification to the original
preliminary plat (SUB-21P-01)to reflect the changes being proposed by the Planned Unit
Development. The subject parcel R3258300000 (approx. 38.07 acres) is located on the SWC of
E Ustick and S Kimball Avenue in Caldwell, Idaho.
Development Plans
1. Development Plans – Prior to commencing construction and applying for building permits,
plans must be prepared by the developer’s engineer and approved by the City Engineering
Department which shall include the following items:
a. Street section and alignment (including curb and gutter);
b. Sidewalk (sidewalk width based on street classification);
c. Sanitary sewer (per City and DEQ requirements);
d. Potable water (per City and DEQ requirements);
e. Stormwater facilities (per City requirements/storm water manual);
f. Street lighting (per City standards);
Soterra #2 & #3
CPM24-000001, DEV24-000001, PUD24-000002, SUB24-000011,
ZON24-000002
Page 2 of 8
g. Street signage (per City and MUTCD requirements);
h. Vertical Datum based on NAVD 88 Datum.
General
1. This project shall comply with all current city codes, standards, policies, and procedures.
2. Easements for Public Utilities shall be 10 feet wide minimum along all front lot lines. A
minimum10 feet wide easement (or larger if deemed necessary by the City Engineer in order to
facilitate future maintenance operations of utilities) may be required along select interior lot
lines to facilitate pressure irrigation or other utilities.
3. Appropriate easements for emergency access, transmission lines and/or other utilities shall be
clearly indicated, with recorded instrument numbers provided for said easements, on the face
of the final plat (visually and in writing). Existing easements shall be shown on all construction
drawings.
4. All utilities on and within the boundaries of the subdivision shall be located and/or relocated
underground.
5. All street, sewer, water, fire protection, and street light facilities must be dedicated to the City.
Some conveyance facilities for stormwater drainage may be eligible for dedication to the City.
6. Construction of facilities to be dedicated and/or within public right-of-way shall be performed by
an appropriately licensed public works contractor and shall be inspected by and constructed to
City of Caldwell specifications.
7. Prior to commencement of construction in any dedicated right-of-way, or construction of any
improvement intended for dedication to the City or connected to a City facility, the City
Engineering staff is to be notified. This preferably will take place in a pre-construction
conference scheduled by the engineer of record in which all appropriate personnel and utilities
are present. Appropriate City personnel are to be notified in advance of all testing (including
compaction, pressure and coliform, etc.) and given opportunity to be present during conduct of
the testing. The engineer of record or his designated representative is to witness all tests (not
covered by City inspectors) and a log of inspection visits and testing results is to be kept by the
engineer of record or his representative.
8. The developer is to employ a responsible design professional, preferably the engineer of
record, to oversee and inspect construction, to perform and/or observe all requisite testing of
completed facilities, and to certify that improvements have been constructed according to
approved plans and in compliance with applicable City, State, and Federal standards.
9. The engineer of record shall be held responsible to ensure that subdivision improvements are
in substantial compliance with said engineer’s design. Following the construction of the
subdivision improvements, the developers engineer shall provide the City of Caldwell
Engineering Department with electronic (.dwg) format record drawings spatially referenced to
Soterra #2 & #3
CPM24-000001, DEV24-000001, PUD24-000002, SUB24-000011,
ZON24-000002
Page 3 of 8
the Idaho State Plane Coordinate System-West Zone, North America Datum (NAD) 83. Vertical
control shall be referenced to the North America Datum (NAVD) 88 for future reference and to
establish that the engineer of record has caused construction to occur in substantial
compliance with the design of said engineer of record.
Rights-of-Way
1. Ustick Road is classified as a Principal Arterial roadway. The applicant shall dedicate as public
right-of-way a minimum forty-eight (48) foot half width right-of-way (from centerline) along the
entire Ustick Road alignment (per City Standard R-810A).
2. Applicant shall provide necessary right-of-way on Ustick Road to construct an eastbound right-
hand turn lane at the intersection of Kimball Avenue. Per standard drawing R-810F
3. Kimball Avenue is classified as a Collector roadway. The applicant shall dedicate as public
right-of-way a minimum thirty-five (35) foot half width right-of-way (from centerline) along the
entire Kimball Avenue alignment (per City Standard R-810C).
4. All interior local streets classified as residential shall be dedicated to the City. The applicant shall
dedicate as public right-of-way a minimum fifty-three (53) foot full width right-of-way (per City
Standard R-810 E).
5. Applicant shall dedicate to the City of Caldwell any required right-of-way along all classified
roadways within 90 days of written request from the City of Caldwell.
6. A note shall be placed on the Final Plat indicating that all rights-of-way are to be dedicated to
the public.
Street
1. Full frontage half street improvements shall be completed to all classified roads adjacent to the
proposed project including (Ustick Rd. and Kimball Ave.) in accordance with all City of Caldwell
standards and specifications improvements shall include (but are not limited to) curb, gutter,
sidewalk, asphalt, streetlights, joint trench, spare communication conduit along classified
roadways, storm drainage facilities, etc.
2. All interior circulation routes proposed within this development shall be a minimum of 26’ in
width measured from face of curb to face of curb.
3. All private internal circulation routes shall fully comply with City of Caldwell standards and be
approved by the Caldwell Fire Marshall.
4. Applicant shall construct westbound left-hand turn lanes on Ustick Rd. at the intersection of
Kimball Ave. and the West entrance to the site.
Soterra #2 & #3
CPM24-000001, DEV24-000001, PUD24-000002, SUB24-000011,
ZON24-000002
Page 4 of 8
5.Applicant is responsible for 25% of the widening of the bridge structure and surface
improvements at the crossing of the Phyllis Canal in the alignment of Ustick Rd. located in the
N.W. corner of the site.
6.No lot/building shall have direct access to/from Ustick Rd or Kimball Ave.
7.Applicant shall coordinate with the United States Postal System to determine a cluster mailbox
unit location. Said location shall be interior to the site and shall be located in a manner that will
not impact, or cause queueing onto, Ustick Rd or Kimball Ave.
7.Applicant shall gain plan approval from Highway District No. 4 (HD#4) for improvement along
HD#4 owned and operated roadways.
a.Any improvements that may be waived by the City Engineer shall also be approved to
be waived by HD#4 Engineer.
Traffic Mitigation
The following are the required traffic related mitigation measures for the Soterra Subdivision
resulting from the traffic impact study pursuant to City Code Chapter 10, Article 10. A traffic
impact study was completed for this development because of the volume of traffic produced.
1.Provide a cross-access easement allowing use of approaches and cross-access of the site
by both onsite and adjacent development.
2.Community Planning Association of Southwest Idaho has computed the average trip length
in Canyon County to be 7.3 mi. Traffic impact mitigation should presumably occur at both
trip ends so ½ of the trip length should be attributed to each end. It is estimated that trips will
encounter a major intersection every half mile along any given path. The capacity of an
average fully improved intersection (assumed to be the intersection of a collector and an
arterial road) is estimated to be 5,080 vehicles/hour.
The estimated traffic resulting from the proposed density in this subdivision based on the
most current Traffic Impact Analysis sets the pm peak hour traffic flow at 226 vehicles for
the entire subdivision.
Following the City of Caldwell’s mitigation equation ((226 veh/hr*7.3 mile/trip*0.5 trip
ends*2inter/mi) / (5080veh/hr)) the total contribution of this development to traffic
mitigation shall be 32.5% of a fully improved intersection. This percentage represents
the total capacity utilized from each intersection (once fully improved and possibly
signalized) encountered by trips generated over the development’s half of the generated
trip length.
a)The owner/developer/applicant shall design and construct roughly 32.5% of the
signalization improvements needed for an average intersection, as defined, at one or
more nearby (within 3.5 miles of the site) deficient locations to be determined by
Soterra #2 & #3
CPM24-000001, DEV24-000001, PUD24-000002, SUB24-000011,
ZON24-000002
Page 5 of 8
Engineering staff. The Engineering staff shall have reasonable discretion to determine
the sites of construction and what design and construction equals roughly 32.5% of the
signalization improvements needed for an average intersection. Engineering staff can
provide information about applications with whose mitigation efforts the
owner/developer/applicant can combine to achieve even units of 100%.
i) The owner/developer/applicant may be allowed, at his option, to contribute monies in
lieu of construction to the City of Caldwell Roadway Trust Fund, but the basis for the
obligation is for construction. Monetary contributions must be made at a level
commensurate with costs to construct the same by the City and as estimated by the
City. This alternate provision for payment of money is not a requirement, is for the
benefit and convenience of the owner/developer/applicant only and does not
constitute an Impact Fee.
ii) The average cost of intersection is estimated at $425,000 for procurement of
design services, construction, and associated costs by the City, of which 32.5% of
that cost is what needs to be covered by this subdivision.
Water
1. All on site water mains will need to be looped into existing mains for fire flow and water quality
purposes. Internal main sizing and construction plan approval, will be dependent upon the
availability of fire flow.
2. Each buildable lot shall be supplied with potable water. If buildings are constructed to include
individual units that could feasibly or will be sold separately, each unit shall be serviced
separately
3. Each phase of development shall have a redundant/secondary supply of domestic water.
4. The location of water service, including sizing of mains, providing of easements, frontage
construction, and offsite construction are to be decided during review of improvement plans.
This development will be required to comply with the Water Master Plan.
a. An 18” Water line is required in the alignment of Ustick Rd. adjacent to this site in
compliance with the Water Master Plan. Applicant shall upsize the existing 12”
water in accordance with the Master Plan or provide monies in-lieu of
construction to be determined by the City Engineer at the time of civil plan
submittal.
Sanitary Sewer
1. It shall be the responsibility of the applicant’s engineer to verify that connection to existing sewer
mainlines will not exceed the functional capacity of said mainlines. Provision for connectivity by
future developments shall be met in accordance with current City standards.
Soterra #2 & #3
CPM24-000001, DEV24-000001, PUD24-000002, SUB24-000011,
ZON24-000002
Page 6 of 8
2. The location of sewer service, including sizing of mains, providing of easements, frontage
construction, and offsite construction are to be decided during review of improvement plans.
3. This development will be required to install a 12” trunk line in Ustick Rd. specified within the most
current version of the Dixie Sewer Study that reside within the limits of this preliminary plat.
4. The Developer will be required (where applicable) to extend all sewer and water mainlines to the
center of adjacent roadways for connectivity by future developments. Locations of said
extensions will be decided during the review of the improvement plans.
5. Each buildable lot shall be supplied with a sewer service. If buildings are constructed to include
individual units that could feasibly or will be sold separately, each unit shall be serviced separately
6. Any easements for sewer lines not in the right-of-way should be at a width sufficient to construct
same and not less than 20 feet in width. Easements for adjacent sewer and water lines not in the
right-of-way shall be at a width sufficient to construct the same and shall be no less than 30 feet
in width.
7. A 20’ wide all-weather surfaces may be required to be constructed over mainlines that fall outside
the public right-of-way. All weather surfaces shall be constructed sufficiently to support heavy
equipment necessary to construct and maintain sewer under all seasonal weather conditions.
Irrigation
1. Existing easements and/or right-of-ways for any irrigation facility shall be determined and
clearly indicated on the construction plans. Construction across or re-routing of these facilities
is subject to approval by the governing irrigation district and at their discretion or their assigns.
2. The Developer shall maintain any existing upstream drainage rights and downstream irrigation
rights across the property. During the design phase of this project, the developer or his
engineer is to contact the appropriate irrigation district to help ascertain these rights.
Appropriate facilities shall be provided by the developer to convey irrigation and drainage water
across the property to take care of these offsite needs. There is to be no discharge of
gravity/pressure irrigation return water into the projects storm water system.
2. The development is to include a non-potable water pressure irrigation system. The design of
this pressure irrigation system is to be reviewed and approved by the Caldwell Municipal
Irrigation District prior to construction plan approval. It shall be required that the system will be
operated and maintained by the Caldwell Municipal Irrigation District.
3. Each lot, or building area, shall be provided with a pressure irrigation service in compliance with
Caldwell Municipal Irrigation District standards.
4. All pressure irrigation mainlines shall be located in the public right-of-way or within a public
utility easement, with a minimum width of 10 feet, centered over said mainlines as per current
City standards.
Soterra #2 & #3
CPM24-000001, DEV24-000001, PUD24-000002, SUB24-000011,
ZON24-000002
Page 7 of 8
5. Applicant shall place the pump station in an area that is easily accessible with a recorded
perpetual easement sufficient for convenient access and maintenance of said pump station.
The lot shall be owned and maintained by the home owners association.
6. The applicant shall ensure that an adequate continuous irrigation supply flow is available to
meet the pressure irrigation system requirements of CMID.
7. The applicant shall transfer a proportionate share of any existing water right(s), except those
held in trust by an irrigation district, to the City of Caldwell for both irrigation and domestic water
supply for the subject development. If this should occur, The City shall assist in registering the
transfer.
8. Applicant shall pipe the pump station delivery ditch from the source point (head gate) to the
pump station. Pump station overflow shall be piped from the pump station to the point of
discharge into an irrigation facility/canal/drain/etc. maintained by an irrigation district.
9. Upon Applicants connection to or use of the existing irrigation pump station, should they
choose to do so and CMID deems it appropriate to connect to, the applicant shall:
a) Supply the City of Caldwell with a water model of the whole pressurized irrigation
system including the piped overflow showing the system design meets all Caldwell
Municipal Irrigation District standards.
b) Applicant shall complete all upgrades to the system as required by CMID. Said
upgrades will be determined during plan review”
10. All plans and construction drawings submitted to the City of Caldwell for review and approval
for any out-of-season irrigation work to be performed within or across facilities located within (or
owned by) irrigation districts other than CMID shall be submitted to the Caldwell Engineering
Department no later than August 15th. Submittal of plans after this date may result in Applicant
not receiving plan approval in time to complete out-of-season work.
Storm Drain
1. As noted previously, provision is to be made for the disposal of stormwater drainage in
accordance with the City Stormwater Management Manual and any updates adopted
subsequent to this application. A copy of this policy is available upon request. The engineer of
record is to provide calculations, which indicate that the assumptions in his stormwater
drainage plan comply with the requirements of the stormwater manual. In this case, if a storm
water system is existing, the burden of proof is on the developer to verify the capacity is
sufficient for the proposed development.
2. The applicant shall identify and retain all historical drainage discharge points from the property
for the purpose of draining on-site storm water detention facilities.
3. Storm water detention basins are required to remain on-site and are to be operated and
maintained by the Home/Business Owners Association/etc.
4. There is to be no discharge of storm water overflow into any irrigation water return/discharge
facility/ditch/pipe/etc.
Soterra #2 & #3
CPM24-000001, DEV24-000001, PUD24-000002, SUB24-000011,
ZON24-000002
Page 8 of 8
Plat
1. Prior to approval of the final plat, subdivision facilities must be completed or an appropriate
construction security provided. There may be temporary restrictions to the obtaining of building
permits, even with acceptable construction security, depending on fire protection, emergency
service requirements, and City approval of the sanitary sewer system. A 20% temporary
restriction to obtaining of building permits will be enforced until all facility construction has been
completed, inspected and certified by the Applicants engineer including all punch list items.
2. A note shall be added to the final plat stating that no lot shall have direct access to/from W.
Ustick Rd. or S. Kimball Ave.
3. Upon recordation of the plat, the Engineering Department is to be provided with a PDF copy
of the recorded final plat and 3 full paper sets.
4. An electronic (dwg.) copy of the Final Plat suitable for mapping and addressing purposes will
be required with Final Plat application submittal.