Memorandum
To: Katie Wright, Planner II
Caldwell P & Z Department
From: TJ Frans, Project Manager
Steven Pendleton, Plans Examiner II
Re: CPM23-000012, ZON23-000010, SUP23-000016 (Domes Church Apartments)
Date: January 12, 2024
The Engineering Department provides the following comments on a request by Kimley-Horn, on
behalf of Domes Church Apartments LLC, is requesting a future land use map amendment to change
the designation of parcels R0265300000 and R0265700000 from Traditional Neighborhood to High
Density Residential, to include approval of Resolution 322-23 associated with CPM23-000012, a
rezone from T-N (Traditional Neighborhood) to R-3 (High Density Residential) with a development
agreement, and a special use permit for an affordable multi-family development with 152-units. The
application is being submitted in conjunction with a Lot Line Adjustment application and a Vacation
application to combine the two existing parcels and adjacent vacated right-of-way into a single parcel.
The site is located just south of Interstate-84, between N. 14th Ave. and N. 16th Ave., in Caldwell,
Idaho.
Development Plans
1. Development Plans – Prior to commencing construction and issuing building permits, plans
must be prepared by the developer’s engineer and approved by the City Engineering
Department which shall include the following items:
a. Street section and alignment (including curb and gutter);
b. Sidewalk (sidewalk width based on street classification);
c. Sanitary sewer (per City and DEQ requirements);
d. Potable water (per City and DEQ requirements);
e. Stormwater facilities (per City requirements/storm water manual);
f. Street lighting (per City standards);
g. Street signage (per City and MUTCD requirements);
h. Vertical Datum based on NAVD 88 Datum.
Domes Church Apartments
CPM23-000012, ZON23-000010, SUP23-000016
Page 2 of 7
Applicant may apply for building permits following 1st review of civil development plans (to be
submitted concurrently with 2nd civil review) and after Caldwell Mapping Department has
issued addressing for the site.
Applicant shall submit an electronic (dwg.) & PDF copy of the project site plan to both Caldwell
Engineering and Caldwell Mapping suitable for mapping and addressing purposes concurrent with the
first submission of civil improvement plans.
General
1. Easements for public utilities shall be as listed below. Easements will be required to be larger if
deemed necessary by the City Engineer in order to facilitate future maintenance operations of
utilities.
a. 10 feet wide minimum.
b. Domestic water only,15 feet wide minimum
c. Sanitary sewer only, 20 feet wide minimum
d. Sewer and water combined, 30 feet wide minimum
i. Note: future permanent structures will not be permitted to be constructed
within any easement granted to the City of Caldwell. Applicant shall
ensure that civil design and easements provided to the City
accommodate current and future construction needs of permanent
structures such as covered parking structures, future buildings, etc.
2. Appropriate easements for emergency access, transmission lines and/or other utilities shall be
clearly indicated, with recorded instrument numbers provided for said easements, on the
construction drawings.
3. All utilities on and within the boundaries of the subdivision shall be located and/or relocated
underground.
4. All street, sewer, water, fire protection, and street light facilities must be dedicated to the City.
Some conveyance facilities for stormwater drainage may be eligible for dedication to the City.
5. Construction of facilities to be dedicated and/or within public right-of-way shall be performed by
an appropriately licensed public works contractor and shall be inspected by and constructed to
City of Caldwell specifications.
6. Prior to commencement of construction in any dedicated right-of-way, or construction of any
improvement intended for dedication to the City or connected to a City facility, the City
Engineering staff is to be notified. This preferably will take place in a pre-construction
conference scheduled by the engineer of record in which all appropriate personnel and utilities
are present. Appropriate City personnel are to be notified in advance of all testing (including
compaction, pressure and coliform, etc.) and given opportunity to be present during conduct of
the testing. The engineer of record or his designated representative is to witness all tests (not
covered by City inspectors) and a log of inspection visits and testing results is to be kept by the
engineer of record or his representative.
Domes Church Apartments
CPM23-000012, ZON23-000010, SUP23-000016
Page 3 of 7
7. The developer is to employ a responsible design professional, preferably the engineer of
record, to oversee and inspect construction, to perform and/or observe all requisite testing of
completed facilities, and to certify that improvements have been constructed according to
approved plans and in compliance with applicable City, State, and Federal standards.
8. The engineer of record shall be held responsible to ensure that subdivision improvements are
in compliance with said engineer’s design. Following the construction of the subdivision
improvements, the developers engineer shall provide the City of Caldwell Engineering
Department with electronic (.dwg) format record drawings spatially referenced to the Idaho
State Plane Coordinate System-West Zone, North America Datum (NAD) 83. Vertical control
shall be referenced to the North America Datum (NAVD) 88 for future reference and to
establish that the engineer of record has caused construction to occur in substantial
compliance with the design of said engineer of record.
9. Any note, item or drawing element on the plats, construction drawings, engineering drawings
and/or design drawings related to the property inconsistent with City Codes, Policies and/or
Ordinances shall not be construed as approved unless specifically addressed and granted by
City Council.
Rights-of-Way
1. Applicant shall vacate existing right-of-way within the site at N. 16th Ave. east along the north
side of the Notus Canal and provide sewer and water easements to cover existing utilities.
Said vacation process must be fully completed prior to issuance of any certificate of occupancy.
2. All interior private internal circulation drive isles shall have a minimum width of 26’ (face of curb
to face of curb) and meet Caldwell Fire Department (CFD) requirements. If wider drive isles are
required by CFD applicant shall meet those requirements.
Street
1. Full frontage half street improvements shall be completed to all roads adjacent to the proposed
project (N. 14th Ave.) in accordance with all City of Caldwell standards and specifications
improvements shall include (but are not limited to) curb, gutter, sidewalk, asphalt, streetlights,
joint trench, spare communication conduit along classified roadways, storm drainage facilities,
etc.
2. All private driveways/drive isles shall fully comply with City of Caldwell standards and be
approved by the Caldwell Fire Marshall.
3. Applicant shall coordinate with the United States Postal System to determine a cluster mailbox
unit location. Said locations shall be interior to the site and shall be located in a manner that
will not impact or cause queuing onto N. 16th Ave.
4. Comments made by Black Canyon Irrigation District for the existing bridge structure on N. 14th
Ave. indicate this structure was not permitted previously and any disruption of said bridge
Domes Church Apartments
CPM23-000012, ZON23-000010, SUP23-000016
Page 4 of 7
would require removal. Applicant shall not perform and frontage improvements within Black
Canon Irrigation District easements adjacent to this structure.
5. It is the applicant’s responsibility to determine the load capacity and ensure capacity, along with
the width of the existing bridge structure accessing this site, meets all Fire Department
requirements prior to approval of site permits.
6. Applicant shall provide MUTCD compliant centerline and fog line striping along N. 16th Ave.
from the access bridge to the site to the E. Elgin St. intersection. Striping shall be placed on
both sides of the roadway.
Traffic Mitigation
The following are the required traffic related mitigation measures for the Domes Church
Apartments resulting from the traffic impact study pursuant to City Code Chapter 10, Article 10.
A traffic impact study will be required for this development because of the volume of traffic
produced.
1. Provide a cross-access easement allowing use of approaches and cross-access of the site
by both onsite and adjacent development.
2. All study area intersections are anticipated to operate at acceptable LOS for both AM
and PM peak hours.
3. Community Planning Association of Southwest Idaho has computed the average trip length
in Canyon County to be 7.3 mi. Traffic impact mitigation should presumably occur at both
trip ends so ½ of the trip length should be attributed to each end. It is estimated that trips will
encounter a major intersection every half mile along any given path. The capacity of an
average fully improved intersection (assumed to be the intersection of a collector and an
arterial road) is estimated to be 5,080 vehicles/hour.
The estimated traffic resulting from the proposed density in this subdivision based on the
most current Traffic Impact Analysis sets the pm peak hour traffic flow at 60 vehicles for
the entire subdivision.
Following the City of Caldwell’s mitigation equation ((60 veh/hr*7.3 mile/trip*0.5 trip
ends*2inter/mi) / (5080veh/hr)) the total contribution of this development to traffic
mitigation shall be 8.6% of a fully improved intersection. This percentage represents the
total capacity utilized from each intersection (once fully improved and possibly
signalized) encountered by trips generated over the development’s half of the generated
trip length.
a) The owner/developer/applicant shall design and construct roughly 8.6% of the
signalization improvements needed for an average intersection, as defined, at one or
more nearby (within 3.5 miles of the site) deficient locations to be determined by
Engineering staff. The Engineering staff shall have reasonable discretion to determine
the sites of construction and what design and construction equals roughly 8.6% of the
signalization improvements needed for an average intersection. Engineering staff can
Domes Church Apartments
CPM23-000012, ZON23-000010, SUP23-000016
Page 5 of 7
provide information about applications with whose mitigation efforts the
owner/developer/applicant can combine to achieve even units of 100%.
i) The owner/developer/applicant may be allowed, at his option, to contribute monies in
lieu of construction to the City of Caldwell Roadway Trust Fund, but the basis for the
obligation is for construction. Monetary contributions must be made at a level
commensurate with costs to construct the same by the City and as estimated by the
City. This alternate provision for payment of money is not a requirement, is for the
benefit and convenience of the owner/developer/applicant only and does not
constitute an Impact Fee.
ii) The average cost of intersection is estimated at $425,000 for procurement of
design services, construction, and associated costs by the City, of which 8.6% of that
cost is what needs to be covered by this subdivision.
Water
1. All on site water mains will need to be looped into existing mains for fire flow and water quality
purposes. Internal main sizing and construction plan approval, will be dependent upon the
availability of fire flow.
2. Each buildable lot/building shall be supplied with potable water. If buildings are constructed to
include individual units that could feasibly or will be sold separately, each unit shall be serviced
separately
3. The location of water service, including sizing of mains, providing of easements, frontage
construction, and offsite construction are to be decided during review of improvement plans.
Sanitary Sewer
1. It shall be the responsibility of the applicant’s engineer to verify that connection to existing sewer
mainlines will not exceed the functional capacity of said mainlines. Provision for connectivity by
future developments shall be met in accordance with current City standards.
2. The Developer will be required (where applicable) to extend all sewer and water mainlines to the
center of adjacent roadways for connectivity by future developments. Locations of said
extensions will be decided during the review of the improvement plans.
3. Each buildable lot/building shall be provided with individual sewer service. If buildings are
constructed to include individual units that could feasibly or will be sold separately, each unit shall
be serviced separately.
4. Any easements for sewer lines not in the right-of-way should be at a width sufficient to construct
same and not less than 20 feet in width. Easements for adjacent sewer and water lines not in the
right-of-way shall be at a width sufficient to construct the same and shall be no less than 30 feet
in width.
Domes Church Apartments
CPM23-000012, ZON23-000010, SUP23-000016
Page 6 of 7
5. A 20’ wide all-weather surfaces may be required to be constructed over mainlines that fall outside
the public right-of-way. All weather surfaces shall be constructed sufficiently to support heavy
equipment necessary to construct and maintain sewer under all seasonal weather conditions.
Irrigation
1. Existing easements and/or right-of-ways for any irrigation facility shall be determined and
clearly indicated on the construction plans. Construction across or re-routing of these facilities
is subject to approval by the Black Canyon Irrigation District and at their discretion or their
assigns.
2. The Developer shall maintain any existing upstream drainage rights and downstream irrigation
rights across the property. During the design phase of this project, the developer or his
engineer is to contact the appropriate irrigation district to help ascertain these rights.
Appropriate facilities shall be provided by the developer to convey irrigation and drainage water
across the property to take care of these offsite needs. There is to be no discharge of
gravity/pressure irrigation return water into the projects storm water system.
2. The development is to include a non-potable water pressure irrigation system. The design of
this pressure irrigation system is to be reviewed and approved by the Caldwell Municipal
Irrigation District prior to construction plan approval. It shall be required that the system will be
operated and maintained by the Caldwell Municipal Irrigation District.
a) If Applicant obtains a City Council approved landscaping plan which minimizes the area
of landscaping requiring irrigation water to the point that the site is compliant with City
Code for the use of potable water for irrigating, and receives an approved City Water for
Irrigation Purposes application from the Water Department Superintendent & Public
Work Director/City Engineer then potable water may be used.
3. Each lot, or building area, shall be provided with a pressure irrigation service in compliance with
Caldwell Municipal Irrigation District standards.
4. All pressure irrigation mainlines shall be located in the public right-of-way or within a public
utility easement, with a minimum width of 10 feet, centered over said mainlines as per current
City standards.
5. Applicant shall place the pump station in an area that is easily accessible with a recorded
perpetual easement sufficient for convenient access and maintenance of said pump station.
The lot shall be owned and maintained by the home owners association.
6. The applicant shall ensure that an adequate continuous irrigation supply flow is available to
meet the pressure irrigation system requirements of CMID.
7. The applicant shall transfer a proportionate share of any existing water right(s), except those
held in trust by an irrigation district, to the City of Caldwell for both irrigation and domestic water
supply for the subject development. If this should occur, The City shall assist in registering the
transfer.
8. The proposed development may utilize an existing pressure irrigation pump station with
approvals from Caldwell Municipal Irrigation District. Any upgrades to the pump station
Domes Church Apartments
CPM23-000012, ZON23-000010, SUP23-000016
Page 7 of 7
necessary to supply the proposed development with pressurized irrigation water is the
responsibility of the Applicant. Should Applicant connect to an approved pump station they
shall supply the City of Caldwell with a water model of the whole pressurized irrigation system
showing that the system design meets all Caldwell Municipal Irrigation District standards.
9. All plans and construction drawings submitted to the City of Caldwell for review and approval
for any out-of-season irrigation work to be performed within or across facilities located within (or
owned by) irrigation districts other than CMID shall be submitted to the Caldwell Engineering
Department no later than August 15th. Submittal of plans after this date may result in Applicant
not receiving plan approval in time to complete out-of-season work.
Storm Drain
1. As noted previously, provision is to be made for the disposal of stormwater drainage in
accordance with the City Stormwater Management Manual and any updates adopted
subsequent to this application. A copy of this policy is available upon request. The engineer of
record is to provide calculations, which indicate that the assumptions in his stormwater
drainage plan comply with the requirements of the stormwater manual. In this case, if a storm
water system is existing, the burden of proof is on the developer to verify the capacity is
sufficient for the proposed development.
2. The applicant shall identify and retain all historical drainage discharge points from the property
for the purpose of draining on-site storm water detention facilities.
3. Storm water detention basins are required to remain on-site and are to be operated and
maintained by the Home Owners Association/etc.
4. There is to be no discharge of storm water overflow into any irrigation water return/discharge
facility/ditch/pipe/etc.
Building Permits
1. Civil construction and building construction may take place concurrently upon confirmation from
the Fire Marshal that infrastructure is sufficient to meet fire safety requirements for access.
Building Permits will be issued upon acknowledgment that safety access requirements have
been met and only after the Engineering Department has issued an approved set of civil
improvement plans. Building occupancy will not be granted until all utility construction has been
completed, inspected, tested, approved by the City (including the completion of all necessary
easements, record drawings, necessary reports, etc) and certified by the Applicants engineer;
including completion all punch list items.
2. Applicant shall submit an electronic (dwg.) copy of the project site plan suitable for mapping
and addressing purposes no later than 30 days prior to submission of the first building permit.