Memorandum
To: Robin Collins, P/Z Deputy director From: T.J. Frans – Project Manager Jeremy Crowhorn – Land Development Inspector Re: Arbor Ridge Phase 5 (SUB21-000035) Date: July 31, 2023 The Engineering Department has reviewed the proposed final plat for Arbor Ridge Phase 5 and provides the
following comments regarding the project and the submitted final plat: 1. The following items must be completed before signing of the final plat. These items cannot be bonded for: a. The water system is operational. The water system has been constructed and pressure tested. Clean
water samples have not been received. Interim as-builts have been approved. b. All weather surfaces are in place. Compaction test and core sample results have been submitted, reviewed and approved for the roadways. c. Street signs have been installed.
d. The sewer system is operational. The Sewer system has been constructed and pressure checked. e. The pressure irrigation system within the public roadway is operational. The pressure irrigation has been pressure tested.
f. The storm drain system located within the public roadway is operational. The storm drain system has been constructed and passed a visual inspection by the City. Interim as-builts have been approved. 2. Construction security will have to be provided for those items which are not among the items listed above
and not yet completed prior to signing of the final plat. 3. The final plat drawing has been submitted to the City of Caldwell and has been reviewed but not yet
approved. The final plat drawing will have to be done in accordance with City codes, policies, and ordinances prior to the City signing the final plat.
4. In an effort to expedite the addressing process of the final plat, the Engineering Dept. requests an electronic copy in AutoCAD format be returned with a revised full set bound copy of the final plat.