HomeMy WebLinkAboutPUBLIC AGENCY PUBLIC AGENCY
ITEM DATE SUBMITTED BY
Memorandum
To: Debbie Root, Senior Planner
From: T.J. Frans—Project Manager
Jake Wells—Engineering Tech I
Re: Delaware Park Subdivision No. 1 Unit No. 9
Date: July 21, 2021
The Engineering Department has reviewed the proposed final plat for Delaware Park Subdivision
No. 1 Unit No. 9 and provides the following comments regarding the project and the submitted final
plat:
1. The following items must be completed before signing of the final plat. These items cannot be
bonded for:
a. The water system is not operational. The water system has been constructed,pressure
tested and clean water samples have not been received. The final plat will not be signed,
and no building permits will be issued until this emergency requirement is complete.
b. All weather surfaces are in place. Compaction test and core sample results have been
submitted,reviewed or approved for the roadways. The final plat will not be signed, and
no building permits will be issued until this emergency requirement is complete.
c. Street signs have not been installed. The final plat will not be signed, and no building
permits will be issued until this emergency requirement is complete.
d. The sewer system is operational. The sewer system has been constructed,pressure tested
and video has been submitted and approved. Interim as-builts have been approved. The
final plat will not be signed, and no building permits will be issued until this emergency
requirement is complete.
e. The pressure irrigation system within the public roadway is operational. The pressure
irrigation system has been constructed and pressure tested.
f. The storm drain system located within the public roadway is not operational. The storm
drain system has been constructed and passed a visual inspection by the City. Interim as-
builts have been approved.
Page 1 of 2 0
2. Construction security,per City Code section 11-04-07,will have to be provided for those items
which are not among the items listed above and not yet completed prior to signing of the final
plat. The City has not agreed on a bond amount for those improvements not yet constructed.
3. The final plat drawing has been submitted to the City of Caldwell and has been reviewed but not
yet approved. The final plat drawing will have to be done in accordance with City codes,
policies, and ordinances prior to the City signing the final plat.
4. After signature and recordation of the final plat the Engineering Department will process
building permits per City Code section 11-04-07(B);processing permits for 90 days, or until
50%of the total building permits ultimately available for this phase of development have been
issued, whichever occurs first. All remaining permits will be released for processing upon final
completion of all required improvements, annexation and dedication.
5. In an effort to expedite the addressing process of the final plat,the Engineering Dept. requests
an electronic copy in AutoCAD format be returned with a revised full set bond copy of the final
plat.
Page 2 of 2